| Floating technical
base Project 326NATO:
--- Class Completed 8
units Ships Project 326
Name |
Yard ¹ |
Laid Down |
Launched |
Commissioned |
Note |
Shipyard ¹402, Molotovsk (since 9.09.1959 Severnoe mashinostroitelnoe predpriyatie, Severodvinsk) – 4 units |
PTB-1 |
¹410 | 26.09.1958 |
6.07.1960 | 13.12.1960 | |
PTB-10 |
¹411 | 10.07.1961 |
10.08.1962 | 6.10.1962 | |
PTB-22 |
¹412 | 20.11.1962 |
16.10.1963 | 30.11.1963 | |
PTB-19 |
¹413 | 20.07.1963 |
23.06.1964 | 25.07.1964 | |
Shipyard ¹199, Komsomolsk-on-Amur
– 4 units | PTB-4 |
¹94 | 16.01.1960 |
6.09.1960 | 21.12.1960 | then
- TNT-4 | PTB-8 |
¹97 | - |
- | 12.1966 | then
- TNT-49 | PTB-24 |
¹96 | - |
- | 12.1964 | then
- TNT-50 | PTB-16 |
¹95 | - |
- | 10.1962 | then
- TNT-16 | General characteristics
- Project 326
Displacement (tons): | Standard: | 3300 |
Full load: | 3930 |
Dimensions (m): | Length: | 92,4 |
Beam: | 13,4 |
Draft: | 4,6 | Speed
(knots): | Non-self propelled | Autonomy
(days): | 45 | Complement: | 59
(9 officers) | Schematics
Floating technical base - Project 326
Modernizations Project 326M – 6 units since 1972: PTB-4 in 1979,
PTB-16 in 1972 in Shipyard named after Leninskogo komsomola, Komsomolsk-on-Amur,
PTB-1 in 1974-75, PTB-10 in 1971-72, PTB-19 in 1972-73, PTB-22 in 1977-78. in
1977-78 Severnoe mashinostroitelnoe predpriyatie, Severodvinsk. Converted to
service of second generation nuclear submarines - upgraded spent fuel handling
and containerized storage facilities for spent technological channels. Technical
tankers: TNT-4 (PTB-4), TNT-16 (PTB-16), TNT-49 (PTB-8), TNT-50 (PTB-24)
Fleets Northern Fleet: PTB-1, 10, 19, 22 Pacific
Fleet: PTB-4, 8, 16, 24 Hull Numbers PTB-1:
ÏÌ-124, 936(1998?) PTB-4: ÏÌ-125 PTB-8: ÏÌ-32, 926 PTB-10: ÏÌ-128
PTB-16: ÏÌ-133 PTB-19: ÏÌ-50 PTB-22: ÏÌ-78, 916(1980), 901, 908 PTB-24:
ÏÌ-80 Decommissioned 1994 – PTB-16 2005
– PTB-19 (1.12) 2008 – PTB-1 (12.09), PTB-10 (28.03), PTB-22 (28.03) 2009
– PTB-24? 2011 – PTB-8? Export --- | |